Director's Monthly Report - December 2015

Telephone Calls - 21,858
Fire Incidents - 811
EMS Incidents - 3,311
Law Enforcement Incidents - 27, 236

Voice Radio Project:
-Cutover took place on 4 January 2016 with all emergency responders operational on the system scheduled for 21 April 2016
-We are 34 months (89%) into the 38 month Implementation Phase.  About 92% of the project implementation tasks have been completed.  So far we have spent $30,981,968 (69%) of the $45,000,000 total project budget.

New CAD:
-Work is focused on response plan updates for fire departments.  Installations have begun on the Mobile Data project.  Network configuration is ongoing.
-CAD and Mobile Data Cutover is targeted for 28 August 2016.

Public Safety Training Campus:
-Last month we hosted 1,155 people at 64 events in the Academic Building.  Last month we hosted one training session in the Tactical Village for YTD total of 82.
-Final construction documents are being reviewed by Facilities and Procurement in preparation for the Law Enforcement Firing Range bid package to be released.

Southeastern Pennsylvania Regional Task Force:
-East Whiteland Fire Company received an amphibious off-road vehicle with Fire and EMS capabilities to reach victims and fires located in difficult terrain and flooded areas.