Telephone Calls - 24,207
Fire Incidents - 1,056
EMS Incidents - 3,460
Law Enforcement Incidents - 30,455
Voice Radio Project:
-The 60-day burn-in period continues with only one minor microwave issue reported at the Chadds Ford tower site.
-Cutover is scheduled for 4 January 2016 with all emergency responders operational on the system scheduled for 21 April 2016.
-We are 32 months (84%) into the 38 month Implementation Phase. About 87% of the project implementation tasks have been completed. So far we have spent $30,860,802 (69%) of the $45,000,000 total project budget.
New CAD System:
-The CAD has been fully configured and is ready for system freeze. Configuration work continues on open items in Mobile for Public Safety - the majority related to NCIC and PennDOT work.
-Installations have begun on the Mobile Data project. Network configuration is ongoing.
-The schedule for CAD and Mobile Data is awaiting finalized project schedule with AT&T. Once a schedule for Mobile Data is finalized we will work with Intergraph to revise the CAD schedule.
Public Safety Training Campus:
-Last month we hosted 2,461 people at 101 events int he Academic Building. Last month we hosted 16 training session in the Tactical Village for YTD total 66.
-Final construction documents for the Law Enforcement Firing Range are being reviewed by Facilities, DES, and Procurement in preparation to be released for bid.
SE PA Regional Task Force:
-Awaiting Delaware County's signature on FFY2015 grant agreement before funds can be spent.