Advanced Technology Projects
-Rebanding:  We are successfully operating on the rebanded channels and the project is expected to be complete in February 2014.
-Voice Radio Project:  Continuing to finalize leases for the 19 sites that we lease tower space.  Work continues on the site construction drawings.  Approval was made on the Factory Acceptance Test Procedures that will be conducted in February.
-New CAD System:  Data and response stream input continues which is a slow process.  The CAD team is working with ACD Telecom and Intergraph to find a solution.

Public Safety Training Campus
-There is a protest against the award of the Tactical Village contract to Fire Training Specialties.  We are working with Procurement, Facilities and the Solicitor to resolve the issue.
-Still waiting on approval from the Federal Transit Authority for funds for the Firing Range.

SE PA Regional Task Force
-The Task Force is concentrating on finalizing the paperwork with PEMA on the 2011 and 2012 Homeland Security grants.