Monthly Report for September, 2012
Statistics:
22,435 Telephone calls / 748 calls per day
784 Fire Incidents
3188 EMS Incidents: BLS = 1430 ALS = 1758
30,414 Police Incidents
Comm 1 was deployed 3 times for events
Projects:
Rebanding:
-the project has resumed following Spring and FCC approval of the $180,000 change order request to cover the cost of continuing problems with the EF Johnson equipment
-based on the delays associated with the change order, this original 36-month effort is now a 45-month project scheduled to complete by the end of December, 2013.
Voice Radio:
-Background work continues on possibly refining the final scope of maintenance services.
New Fire/EMS Paging System:
-coverage testing was successfully completed last month
-the paging units are being distributed to the firefighters and EMTs this month
-cutover should be completed on October 16
Public Safety Training Campus (PSTC):
-site work on the Tactical Village should begin this month
-expecting a "guidance letter" from U.S. Dept. of Transportation that will outline how we can proceed with spending the $3.7million DOT Grant to begin the Range Project.
-Since opening on Sept. 9th, we have hosted 447 people who attended 11 meetings and 18 training classes.