Telephone Calls - 21,486
Fire Incidents - 880
EMS Incidents - 3,633
Police Incidents - 27,847
Voice Radio Project:
-Of the 27 tower sites we will be using, we have completed the legal and financial process at 23 sites and have released the sites to Harris for their work to begin.
-Cutover is scheduled for 1 January 2016 with Final System Acceptance 21 April 2016.
-Harris held two P25 System Administrator training sessions for County Staff, Metropolitan Communications and ACD Telecom.
New CAD System:
-Fire and EMS data and generic response stream input has been completed. Police have been completed.
-A majority of efforts in December and January were spent getting amendments finalized with Intergraph. The Commissioners approved the upgrade amendments to Version 9.3 on 29 January.
-A new schedule is being generated. The new agreed upon cutover date is September 2015 with final project completion estimated January 2016.
Training Facility:
-Kiddie Fire Trainers continues to work on installing the burn props in the drill tower. The Tactical Village is on track to be operational in April.
-Facilities, Finance, Procurement, DES and the emergency responders continue working with Manns Woodward to design the Law Enforcement Firing Range. We anticipate construction bid documents being issued in April and construction beginning late summer.
-Last month we hosted 877 people at 40 events.
Thursday, February 5, 2015
Director's Report for January 2015
Wednesday, January 14, 2015
Director's Report - December 2014
Telephone Calls - 21, 912; 707 per day
Fire Incidents - 773
EMS Incidents - 3,447
Police Incidents - 25,903
Voice Radio Project:
-Of the 27 tower sites, we have completed the legal and financial process at 21 sites and have released the sites to Harris for their work to begin
-The fully-redundant Network Switching Centers, the brains of the radio system, were brought on-line and are communicating with each other at the GSC and the Forestville Tower
-Harris held two P25 System Overview training sessions for County Staff, Metropolitan Communications, ACD Telecomm, and emergency responders
New CAD System:
-Data and response stream input continues. Police have been completed.
-Responder input (Police, Fire and EMS) for Mobile Data configuration continues.
-A map update workshop was held.
Training Facility:
-Construction of buildings in the Tactical Village has been completed. Electrical, mechanical, plumbing, and gas fire prop work continues. The Tactical Village is on track to be operational in April.
Southeastern PA Regional Task Force:
-The Chester County Health Department received Medical Field Clinic Trunks. These trunks bring medical supplies and equipment into the community during a public health emergency and better equip them to serve a role when deployed to a Red Cross shelter.
-The Chester County Detectives received computer forensics software. This software better equips them to examine portable devices such as cellular telephones.
Monday, December 15, 2014
Chester County Employee Graduates from FEMA’s Emergency Management Institute
Emmitsburg, MD- Heather Morgan, Training and Exercise Coordinator
for the Chester County Department of Emergency Services graduated from the
Federal Emergency Management Agency’s (FEMA) National Emergency Management
Basic Academy at the Emergency Management Institute (EMI) on September 18,
2014.
EMI has created the National Emergency Basic Academy to produce a
comprehensive curriculum that provides the foundational knowledge and skills
needed to support the unpredictable challenges in the field of emergency
management.
Morgan completed the five courses in the Basic Academy that
includes Foundations of Emergency Management; Science of Disaster; Planning:
Emergency Operations; Exercise Design; and Public Information and
Warning. To graduate, she fulfilled a total of
167 hours of training.
The Basic Academy is the first phase of FEMA’s new Emergency
Management Professional Program (EMPP). The EMPP curriculum is designed
to be a lifetime of learning for emergency managers and includes three
separate, but closely related, training programs. The National Emergency
Management Basic Academy is a gateway for individuals pursuing a career in
emergency management. The National Emergency Management Leaders Academy is
designed for emerging leaders and mid-level managers who lead emergency
management programs and want to advance their skillset. The Executive Academy
is designed for senior-level executives who are responsible for making
decisions that have a significant effect on prevention, protection and mitigation
policy or the management of disaster response and recovery.
This
past week, Heather received a citation from the Commissioners for her continued
dedication to ensure the safety of Chester County citizens.
Amy
Kate Amer
Community
Outreach Coordinator
Chester
County Department of Emergency Services
DES Employee wins Award for his Map 2nd Year in a Row
West
Chester, PA
– At the ESRI International Conference held in San Diego, CA, this past July,
Dave Sekkes, Emergency Planning Coordinator for DES was honored with a first
place award for Best Analytic Presentation.
As
a part of the ESRI International Conference they offer a Map Gallery. The
Map Gallery consists of 13 categories and provides an opportunity for
conference attendees to share GIS work by showcasing innovative printed
maps.
Dave
received the Best Analytic Presentation. This judges entrants on
communication of the problem/project to be solved; presentation of the analytic
procedures; relevance of the problem-solving methods to the analysis –
complexity and logic of analysis; and, integration of cartographic principles
with analytic processes.
For
his submission, Dave performed an analysis of the 164 emergency warning sirens
that have been strategically placed throughout the three-county Limerick
Generating Station Emergency Planning Zone.
In
the event of a siren failure during an emergency at the Limerick plant, local
fire companies will perform what’s known as “route alerting” as an alternative
means to notify the public. Dave utilized GIS to explore updating the
route alert sectors in order to optimize the efficiency of the response to a
siren failure. The study found that 40% of the Emergency Planning Zone
had redundant siren coverage and the drive-times to alert the public could be
greatly reduced by focusing the alerting to those areas without redundant
coverage.
This
is the second consecutive year that Dave has won an award for his maps at this
conference. Last year, Dave won a first place award for Best Data
Integration where he examined the Marsh Creek Dam inundation zone using new
building footprint software.
Dave
utilizes the GIS to provide analysis and mapping support in the Emergency
Operations Center (EOC) during activations and to the department as a whole
during daily operations. Additionally, Dave provides technical support
for department IT initiatives. Dave has worked with GIS at Chester County
since 2002 beginning with the Health Department and joining DES in 2008.
This
past week, Dave received a citation from the Commissioners for his continued
award winning maps.
Amy
Kate Amer
Community
Outreach Coordinator
Chester
County Department of Emergency Services
Tuesday, December 2, 2014
Director's Report - November 2014
For the month of November, 2014:
Emergency Telephone Calls - 21, 827
728 Per Day
Fire Incidents - 889
EMS Incidents - 3,124
Police Incidents - 26,547
Voice Radio Project:
-Of the 27 tower sites we will be using, we have completed the legal and financial process at 21 sites and have released these sites to Harris for their work to begin.
-Site construction has begun at 17 sites.
CAD Project:
-Data and response stream input continues
-Responder input (Police, Fire and EMS) for Mobile Data configuration continues
-New request for additional interface with Knowledge Center
-Investigating new enhancements for capabilities
Training Facility:
-Construction continues at the Tactical Village. Last month the Drill Tower and Burn Building structural work was completed.
-Design meetings for the firing range with architect, facilities and emergency responders continue.
-Last month we hosted 1,506 people at 71 events.
Tactical Village Construction pictures can be seen on our website at www.chesco.org/des
Thursday, October 2, 2014
Director's Report - September 2014
Telephone Calls for the month - 23,883 796 per day
Fire Incidents - 814
EMS Incidents - 3,344
Police Incidents - 28,103
Voice Radio Project:
-Of the 27 tower sites we will be using, we have completed the legal and financial process at 20 sites and have released the sites to Harris for their work to begin.
-Site construction has begun on 15 sites.
New CAD Project:
-Data and response stream input continues.
-Responder input for Mobile Data configuration continues
-New request for additional interface with Knowledge Center
-Investigating new enhancements for capabilities
Public Safety Training Campus:
-Construction continues on the Tactical Village. The Drill Tower fourth floor has begun and the Burn Building upper floors completed. Visit our website for pictures - www.chesco.org/des
-Preliminary design meeting for the firing range was held with the Architect, County Facilities Department and emergency responders.
-Last month we hosted 1,861 people at 62 events.
SE PA Regional Task Force:
-188-portable Honda Generators were distributed to 38 municipalities' public works departments and emergency management agencies throughout the County. These generators were ear marked to assist municipalities in keeping their traffic lights operational during large power outages. The following municipalities received these generators:
Atglen Borough Schuylkill Township
Birmingham Township South Coventry Township
Caln Township Spring City Borough
Charlestown Township Tredyffrin Township
City of Coatesville Uwchlan Township
Downingtown Borough Valley Township
East Bradford Township West Chester University
East Brandywine Township West Bradford Township
East Goshen Township West Brandywine Township
East Whiteland Township West Caln Township
Honey Brook Borough West Chester Borough
Kennett Square Borough West Fallowfield Township
London Grove Township West Grove Borough
Malvern Borough West Pikeland Township
New Garden Township West Sadsbury Township
North Coventry Township West Vincent Township
Parkesburg Borough West Whiteland Township
Penn Township Westtown Township
Phoenixville Borough Willistown Township
Fire Incidents - 814
EMS Incidents - 3,344
Police Incidents - 28,103
Voice Radio Project:
-Of the 27 tower sites we will be using, we have completed the legal and financial process at 20 sites and have released the sites to Harris for their work to begin.
-Site construction has begun on 15 sites.
New CAD Project:
-Data and response stream input continues.
-Responder input for Mobile Data configuration continues
-New request for additional interface with Knowledge Center
-Investigating new enhancements for capabilities
Public Safety Training Campus:
-Construction continues on the Tactical Village. The Drill Tower fourth floor has begun and the Burn Building upper floors completed. Visit our website for pictures - www.chesco.org/des
-Preliminary design meeting for the firing range was held with the Architect, County Facilities Department and emergency responders.
-Last month we hosted 1,861 people at 62 events.
SE PA Regional Task Force:
-188-portable Honda Generators were distributed to 38 municipalities' public works departments and emergency management agencies throughout the County. These generators were ear marked to assist municipalities in keeping their traffic lights operational during large power outages. The following municipalities received these generators:
Atglen Borough Schuylkill Township
Birmingham Township South Coventry Township
Caln Township Spring City Borough
Charlestown Township Tredyffrin Township
City of Coatesville Uwchlan Township
Downingtown Borough Valley Township
East Bradford Township West Chester University
East Brandywine Township West Bradford Township
East Goshen Township West Brandywine Township
East Whiteland Township West Caln Township
Honey Brook Borough West Chester Borough
Kennett Square Borough West Fallowfield Township
London Grove Township West Grove Borough
Malvern Borough West Pikeland Township
New Garden Township West Sadsbury Township
North Coventry Township West Vincent Township
Parkesburg Borough West Whiteland Township
Penn Township Westtown Township
Phoenixville Borough Willistown Township
Tuesday, July 8, 2014
Director's Report - June 2014
Telephone calls - 24,480 for month -- 816 per day
Fire Incidents - 829
EMS Incidents - 3,260
Police Incidents - 28,155
Voice Radio Project:
-15 tower sites have been released to Harris for their work to begin
-Tower strengthening has been completed at Pocopson and Government Services Center sites
-We are exploring options regarding a microwave system router obsolescence issue.
CAD Project:
-Data and response stream input continues
-Working with EMS to utilize AVL responses for 2nd due
-Responder input for mobile data configuration continues
-Continuing to work on interfaces to replace Glynare paging terminals
Public Safety Training Campus:
-Construction continues at the Tactical Village.
-Second floor of Drill Tower completed
-Foundation for Burn Building has been started
-Block walls are being erected for the Admin Building/Outdoor classroom
-Work continues on the garages
Submitted by
Acting Director John Haynes
Fire Incidents - 829
EMS Incidents - 3,260
Police Incidents - 28,155
Voice Radio Project:
-15 tower sites have been released to Harris for their work to begin
-Tower strengthening has been completed at Pocopson and Government Services Center sites
-We are exploring options regarding a microwave system router obsolescence issue.
CAD Project:
-Data and response stream input continues
-Working with EMS to utilize AVL responses for 2nd due
-Responder input for mobile data configuration continues
-Continuing to work on interfaces to replace Glynare paging terminals
Public Safety Training Campus:
-Construction continues at the Tactical Village.
-Second floor of Drill Tower completed
-Foundation for Burn Building has been started
-Block walls are being erected for the Admin Building/Outdoor classroom
-Work continues on the garages
Submitted by
Acting Director John Haynes