Voice Radio Project:
-Harris has completed 55% of mobile installs and 35% of control station installs.  All installation work is scheduled to be completed by 21 April 2016.  SSC Consulting and Chester County will be following up after installations are complete at an organization to ensure everything is satisfactory.  Do not call Metropolitan Communications about installation issues.
-Reports of system issues and programming errors are being addressed by Harris.  An adjustment has been made to alarm threshold.  Issues with "CC Scan" should be resolved; however, if agencies experience "CC Scan" please report through Enterprise Wizard.
-We are 36 months (95%) into the 38 month Implementation Phase.  About 96% of the  project implementation tasks have been completed.  So far we have spent $32,594,412 (72%) of the $45,000,000 total project budget.

New CAD System:
-Work is focused on response plan updates for fire departments
-Installations have begun on the Mobile Data project.  So far 317 of 755 (42%) have been installed.  Network configuration is ongoing.
-CAD and Mobile Data Cutover is targeted for 28 August 2016.

Public Safety Training Campus:
-Last month we hosted 1,426 people at 62 events in the Academic Building and hosted two training sessions in the Tactical Village.
-Final construction documents are being reviewed by Facilities and Procurement in preparation for the Law Enforcement Firing Range bid package to be released.

Southeastern PA Regional Task Force:
Fifteen trailer-mounted light towers and 70 "Emergency Scene Ahead" fold and roll signs were distributed to fire police.