Director's Report for November, 2016

Telephone calls - 22,169
Fire Incidents - 941
EMS Incidents - 3,312
Police Incidents -29,356

Voice Radio Project:
-Harris working on clean-up items related to radio programming and install work.  Second touch programming has begun.  Speaker Microphone replacements will coincide with second touch programming.  GPS and standard microphones are being replaced, regardless of whether County or agency-owned.  Firefighter microphones (yellow) are not being replaced.

-We are working with AT&T to resolve a tower space issue before moving forward with the Wayne enhancement site.  Harris is working on a preliminary design and cost for West Chester Borough Police.

-We are 45 months (98%) into the 46 month Implementation Phase.  About 99% of the project implementation schedule has been completed.  So far we have spent $37,906,199 (84%) of the $45,000,000 total project budget.

New CAD:
-MPS reassessment workshops have been completed.  Integraph and DES are working with responder representatives on testing the requested changes.  An estimate of effort is being developed for additional changes that have been requested, but not completed, by Intergraph.

-Now that all of the premise data has been entered into the Special Address database, DES is prepping to roll out an updated CAD and MPS map.  This map roll will allow AVL recommendations to switch from straight-line to routable distance.  This will also provide for better out of county unit recommendations by AVL.

-DES is working on new response plans to provide a better second due territory for areas with split territory such as 55/187; 93/193; 94/194, etc.

Public Safety Training Campus:
-Last month we hosted 1.903 people at 74 events in the Academic Building.  Last month we hosted 46 training sessions in the Tactical Village for a YTD total of 292.  A new sign was installed along Modena Road marking the Public Safety Training Campus.

-The foundation wall is well underway for the firing range.  The secondary parking lot is expected to be completed by the end of December.