Tuesday, July 8, 2014

Director's Report - June 2014

Telephone calls - 24,480 for month -- 816 per day
Fire Incidents - 829
EMS Incidents - 3,260
Police Incidents - 28,155

Voice Radio Project:
-15 tower sites have been released to Harris for their work to begin
-Tower strengthening has been completed at Pocopson and Government Services Center sites
-We are exploring options regarding a microwave system router obsolescence issue.

CAD Project:
-Data and response stream input continues
-Working with EMS to utilize AVL responses for 2nd due
-Responder input for mobile data configuration continues
-Continuing to work on interfaces to replace Glynare paging terminals

Public Safety Training Campus:
-Construction continues at the Tactical Village.
     -Second floor of Drill Tower completed
     -Foundation for Burn Building has been started
     -Block walls are being erected for the Admin Building/Outdoor classroom
     -Work continues on the garages


Submitted by
Acting Director John Haynes